Construction Authority Signs Design-Build Contract for Foothill Gold Line

On the steps of Pomona City Hall - and surrounded by hundreds of elected officials and community stakeholders - the Foothill Gold Line Construction Authority signed the Glendora to Montclair project’s design-build contract on October 4, 2019 (see photo below).  The Kiewit-Parsons team was awarded the contract that includes an $805.6 million base scope for the first nine miles of the project from Glendora to Pomona, with a two-year contract option to complete the full 12.3-mile project to Montclair for a total contract award of $1,186.9 million if additional funds are secured by October 2021.
With the contract awarded and signed, Kiewit-Parsons is now underway with their work. The first many months will be spent finalizing design and conducting pre-construction activities that will inform the design before major construction starts next Summer.

 
The following pre-construction activities will be starting as early as November 2019:

  • Geotechnical borings to understand the soil conditions at future bridge and overhead catenary system pole foundation locations
  • Geotechnical borings to understand soil conditions near future storm water infiltration basins
  • Surveying of the entire rail right-of-way, and
  • Potholing to verify utilities
Most of the pre-construction activities to be conducted will occur within the railroad corridor; however, some will need to occur at street crossings, requiring short term lane closures.  The construction crews are scheduled to work weekdays during normal business hours.   
Major construction is expected to begin next Summer.  It is anticipated that the initial phase from Glendora to Pomona will take five years to complete and be ready to turn over to LA Metro for passenger service in 2025. If the additional funding needed is secured, and the contract option initiated, the entire project to Montclair will be completed altogether and be ready to turn over for passenger service in 2028. 

Project Video Now Available - The Construction Authority has just released a six-minute video, Foothill Gold Line's Journey Continues, that provides an overview of the current state of the 12.3-mile Foothill Gold Line from Glendora to Montclair, insight from Construction Authority Board Chair and Pomona Mayor Tim Sandoval, plus a preview of the work leading up to and during the major construction phase that will begin in Summer 2020. To watch the video click here or go to www.foothillgoldline.org.
Sign-Up to Stay Updated – The Construction Authority plans to host community open houses in Glendora, La Verne, San Dimas and Pomona in Spring 2020 and is also developing interactive construction maps. To stay updated on these and other important project developments, we encourage anyone impacted by the project to sign-up to receive project and construction updates at: www.foothillgoldline.org.    
 
 
 
Have Questions about the Foothill Gold Line?
 
Questions about Construction - For questions regarding the pre-construction activities please call/text the new Foothill Gold Line Construction Hotline at (626) 513-5788 or email communityrelations@Kiewit-Parsons.com.
 
Questions regarding the Foothill Gold Line Project – For general project questions, please call/email the Construction Authority - Yesenia Arias at (626) 305-7012, yarias@foothillgoldline.org
 
 
 
 
It is easy to stay updated on the Foothill Gold Line. Sign up to receive construction alerts and
E-News Updates on the project at - www.foothillgoldline.org.